Sprint: Core Switch/Regional Data Center

BACKGROUND

This Kansas City building houses legacy wireline, data, and core wireless network equipment and has evolved from a long distance switch to a Regional Data Center supporting Sprint’s new Network Vision Plan. Through this plan, upgrades to the Holmes Street Switch and other similar sites allow Sprint to decommission many other facilities, and thus reduce Sprint’s overall energy consumption significantly.

More

Due to the nature of business at Sprint, 87% of electricity consumption by the company derives from the Sprint Network. With a focus on new technologies, Sprint developed the Network Vision Plan which increases efficiency at select sites while enabling decommissioning of 30,000 cell sites and 48 wireless switch facilities across the country. Network Vision will continue to enable energy efficiencies through IP based networking and service “layering” using the Network’s 800, 1900, and 2500 MHz spectrum while supporting future wireless technology advances. The Network Vision program has reduced network energy intensity more than fivefold to 0.45 MWh per Terabit by year end 2013.

Less

SOLUTIONS

The Network Vision Plan is a strategy that includes network upgrades, advancements in power and performance efficiencies, portfolio right sizing, operational changes, and building upgrades. Building efficiency projects include: HVAC variable frequency drive (VFD) upgrades (12,406,496 kBTU/yr); lighting management system and external LED lighting improvements (2,132,025 kBTU/yr); and DC rectifier upgrades (2,416,764 kBTU/yr).

More

Projects were identified through an EnergyMaster™ Site Assessment. All improvements identified in the assessment were evaluated against the return on the required investment and their scalability.

Less

OTHER BENEFITS

Through Network Vision, Sprint is shutting down 30,000 cell sites and 48 switch sites required to support the legacy iDEN network. In doing so, Sprint expects to save more than 727,994 MWh hours of energy consumption and 450,035 MT of CO2-e of greenhouse gas emissions annually.

More

Annual Energy Use

(Source EUI )
Baseline
1.0
Expected
0.93

Energy Savings:

7%

Annual Energy Cost

Baseline
1.0
Expected
0.93

Cost Savings:

7%

Across Network Use

Baseline (Source EUI)
1.0
Expected
0.8

Energy Savings:

20%

Across Network Cost

Baseline
1.0
Expected
0.8

Cost Savings:

20%

Sector Type

Commercial, Data Center

Location

Kansas City, Missouri

Project Size

$68,000 square feet

Financial Overview

Project cost $1.07 Million

Chilled water pumps with VFDs
Chilled water pumps with VFDs

Controls
Controls

VFDs on computer room air handler units
VFDs on computer room air handler units

Ferro-resonant rectifiers replaced with switch mode rectifiers
Ferro-resonant rectifiers replaced with switch mode rectifiers