Skip to main content
Better Buildings Initiative
Solutions
Decarbonization
Emissions Reduction Planning
Energy Efficiency
Renewable Energy & Low Carbon Fuels
Electrification
Carbon Capture, Utilization, and Storage
Funding
Financing Navigator
Funding and Incentives Resource Hub
Water & Waste
Resilience
Workforce Development
Programs & Partners
Better Climate Challenge
Better Buildings Challenge
Better Plants
Partner List
Sectors
More Ways to Participate
Accelerators
Alliance
Home Energy Score
Water Savings Network
Waste Reduction Network
50001 Energy Management Systems
Onsite Energy
Technology Campaigns
Technology Research Teams
Residential Network
Leadership
Goal Achievers
Better Project & Better Practice Awards
Climate Finance Innovation Awards
Road Show
Decarbonization Download
SWAP
Events & Webinars
Summit
Events & Webinars Calendar
Better Buildings Webinars
On-Demand Webinars
E-Learning Center
Newsroom
Just Added
Announcements & Press Releases
Annual Reports
Beat Blog
The Bulletin
Subscribe
Join
Lineage Logistics: Blast Freezing Process and Design Optimization
Energy
Water
Plant Electricity
In Building
Across Network
GHG
Technology
ANNUAL ENERGY USE
ANNUAL ENERGY COST
(Source does not include additional annual operational savings of $425,000)
ANNUAL WATER USE
ANNUAL WATER COST
ANNUAL PLANT ELECTRICITY USE
ANNUAL PLANT ELECTRICITY COST
IN BUILDING ENERGY USE
IN BUILDING ENERGY COST
ACROSS NETWORK USE
ACROSS NETWORK COST
ANNUAL EMISSIONS
USE
COST
Related Content
Implementation Model
University of Utah Health: Using RCx and EMIS to Optimize and Manage Performance
Showcase Project
Havertys: Virginia Beach Showroom #0193
Showcase Project
Dysart Unified School District: Kingswood Elementary School
Webinar
Back by Popular Demand: The Best of the 2019 Better Buildings Summit
Warehousing and Storage
Lineage Logistics
Oxnard
Compressed Air Systems
HVAC
Better Buildings, Better Plants Challenge
Better Plants Program
Better Project Awardee
Industrial
Solution Type
Showcase Project
Sector Type
Industrial
Location
Oxnard, California
Financial Overview
Project Cost $1,800,000